Startup meeting agenda: roof contractor
Agenda for the first meeting on site — everything that needs to be clarified before the first roll is laid
Use the agenda as the notice of meeting and write the decisions directly under each item — then the minutes are ready when the meeting ends. Participants typically include the site manager the roofing master/conductor the foreman/crew chief and possibly the client's representative and workplace environment coordinator.
§1. Project basis
- 01Valid drawings, roof plan and tile plan — version and date confirmed.
- 02Roof build-up and system solution: membrane type, insulation, fastening, fire class (BROOF(t2) documentation).
- 03What instructions are followed (manufacturer's system instructions, PTM instructions, BUILD)?
- 04Interfaces with other trades: flashings, skylights, roof technology, lightning conductors.
§2. Safety and working environment
- 01Faldsikring: hvem etablerer og vedligeholder rækværk/skærme, og efter hvilken klasse (DS/EN 13374)?
- 02Access ways to the roof: stairwell, scaffolding, ladder — and escape routes.
- 03Cordoning below the work area against falling materials.
- 04Holes in the roof surface (skylights, openings): protection against falling through.
- 05Hot work: agreement form, certificates, fire watch and extinguishing equipment — who provides what?
- 06Plan for Safety and Health (PSS): the main contractor's points are reviewed.
- 07Weather limits: when is work stopped (wind, icing, thunder warning)?
§3. Logistics and materials
- 01Crane/hoist times and load zones on the roof (point load! Rolls and pallets must not overload the deck).
- 02Storage area: rolls upright, dry and protected; gas cylinders in approved depot.
- 03Waste management: container for cardboard scraps, granulate and packaging.
- 04Current, water and crew facilities.
§4. Time and process
- 01Timeline with milestones: vapour barrier closed, insulation, underlay, overlay, details, delivery.
- 02Sequence of roof surfaces/phases and requirement for closed roof at the end of the day.
- 03Notification of inspections: which checks will the site manager see before closing?
§5. Quality assurance and delivery
- 01QA form and photo documentation: scope and format agreed (see trade's QA form for roof paper covering).
- 02Tightness check: method and timing — especially if the roof is to be covered (green/inverted roof).
- 03Deviation procedure: how are deviations from the project reported and approved?
- 04Operation and maintenance materials for the client.
| Point | Beslutning/aftale | Responsible | Deadline |
|---|---|---|---|
| Railing established and checked | |||
| Hot work agreement form signed | |||
| Wedge plan delivered to the crew | |||
| QA form and photo requirements agreed | |||
| Next building meeting |