Checklist: preparation before excavation near cables

From LER posting to marking in the field

Excavation work near buried cables requires preparation every single time — even if you have dug at the site before. Use this checklist to ensure no important step is forgotten.

§Before you drive out

  • 01Check the LER (Line Owner Register) for the current area
  • 02Procurement and suppliers
  • 03Contact the network company if the information is unclear or incomplete
  • 04Book any professional marking well in advance of the task

§On site

  • 01Check physical marking against received conductor information
  • 02Use hand excavation or other careful methods close to known utilities
  • 03Have first aid equipment and correct protective equipment ready
  • 04Inform colleagues and any contractors about the location of known cables

§When the work is complete.

  • 01Restore marking and document any changes in routing
  • 02Report any damage to third-party cables immediately to the cable owner
  • 03Update own documentation if new wiring or cables have been laid

The cable you never found out was there is the one you are going to dig into.