Work process: Laying of covering

From base layer to finished durable surface

§1. Base and bearing layer

  • 01Dig out to the right depth.
  • 02Læg og komprimér bærelag i lag.
  • 03Establish proper slope so water drains away.

§2. Finishing coat

  • 01Lay geotextile/fibre cloth if needed to separate raw soil and bearing layer.
  • 02Pull it off at the correct height and angle.
  • 03Beware not to step in the finished dressed layer.

§3. Laying the stones

  • 01Læg sten/fliser i det valgte mønster med jævne fuger.
  • 02Place edgings along the sides.
  • 03Check lines, gradient and height continuously.

§4. Grouting and finishing

  • 01Sweep joint material down into the joints.
  • 02Vibrate the pavement so the stones lock together.
  • 03Post-wet and clean the surface.